Hendaye (64)
Removal of four sailboat wrecks in Chingoudy Bay
In Chingoudy Bay in Hendaye, SIDON removed four sailboats abandoned at their moorings and handed them over to an approved boat demolition scheme.
Background
In Chingoudy Bay, in Hendaye, four sailboats had been abandoned at their moorings. Working for a French State service, SIDON was asked to take them out of the water and have them demolished through an approved scheme.
Bringing the boats into the harbour
On 18 November, the four sailboats were brought into Hendaye harbour. Two of them were emptied of their waste and left afloat at the pontoon until they could be lifted. The other two were lifted by crane the same day and set on cradles in the technical area, to rule out any weather risk before loading.
Emptying and unstepping the masts
The waste left on board the four boats was gathered on the quay, then taken to an approved treatment centre in Anglet: 120 kg of non-hazardous waste, with a weighbridge ticket. On 19 November, the masts of all four sailboats were unstepped.
Lifting and transport
Each sailboat was loaded onto the trailer of a specialist haulier, as an oversize load, bound for an approved demolition centre in Mérignac, Gironde. The first was lifted with the marina's boat hoist on 19 November; the last boat still afloat was lifted on the morning of the 20th.
Why an approved scheme
An end-of-life pleasure boat is demolished in an approved centre, where materials are sorted and hazardous waste is treated separately. Left at its mooring, a wreck deteriorates, gets in the way of other water users and eventually sinks with everything it contains.
Outcome
By 20 November, the four sailboats had left Chingoudy Bay: the mooring area is clear and the wrecks are going through the demolition scheme.
Other projects
La Terrasse-sur-Dorlay (42)Installation of staff gauges at the Dorlay dam
Two staff gauges and their elevation plates installed at more than 20 m on the dam face, in water at 6 °C, by touch.
Read the case study
Coulommiers (77)Restoration of two masonry bridges on the Grand Morin
Two masonry bridges on the Grand Morin: four big-bag cofferdams, 250 m² of repointing and low-pressure grout injection.
Read the case study
Hendaye (64)Refloating a sailing boat in a Natura 2000 area
Sailing boat aground for nearly a year on the Île aux Oiseaux: refloated with lift bags, then demolished, with materials sorted through a recycling route.
Read the case studyPhotos from our sites
Photos taken on our job sites.





A structure in contact with water? Call us.
Describe it in a few lines: a technical manager will call you back to define the need and price the job.