Hendaye (64)

Inspection and replacement of the mooring area buoys in Hendaye

In Chingoudy Bay, SIDON inspected and marked the seven buoys of the Hendaye mooring area, put two buoys back in place and installed a new mooring line.

7 buoysinspected and marked
2 buoysput back in place
1 linenew mooring line

Background

The light-equipment mooring area (ZMEL) of Hendaye, in Chingoudy Bay, is marked out by zone buoys. Working for a French State service, SIDON inspected these buoys, put back the two that had been removed and updated their markings.

Putting two buoys back in place

Buoys A and C were collected on 18 November and put back at their positions. Buoy C was given a new mooring line: galvanised chain, new swivel and shackles, all moused. Buoy A was set back on its original sinker, with its existing rope, which was in good condition.

Marking and righting

The seven zone buoys, A, B, C, D, E, H and I, were marked with their letter and the identification of their operator. Ballast was added to all the buoys to make them float upright.

Buoy-by-buoy condition

Each buoy was recorded with its GPS position and condition. Six are in sound condition; buoy I, worn, is flagged for monitoring in the file handed over at the end of the works.

Long-term follow-up

SIDON knows these moorings: in March 2024, our divers had already installed the lines of buoys D, H and I. The as-built file records how these lines are made up, which prepares future inspections.

Outcome

On 21 November 2026, the seven buoys of the mooring area were in place, marked and ballasted, at their positions.

In the field

Photos from our sites

Photos taken on our job sites.

Zone buoy C back in place in Chingoudy Bay
Buoy C and its new galvanised chain mooring line
New swivel and shackles, moused
Buoy H marked, inspected from the boat
Buoy E marked and cleaned