# Emergency work on a pump in a wastewater treatment plant in Aramon

> In Aramon (Gard), SIDON divers made an emergency dive, with zero visibility, in the aeration tank of an industrial wastewater plant to bring out a pump.

[Home](https://www.sidon-construction.fr/en) / [Projects](https://www.sidon-construction.fr/en/projects) / Aramon (30)

Aramon (30)

In Aramon (Gard), SIDON divers made an emergency dive, with zero visibility, in the aeration tank of an industrial wastewater plant to bring out a pump.

**5 days** · from the first call to the dive

**1 day** · on site, on 24 November 2026

**Zero visibility** · under a layer of foam and sludge

## Background

At an industrial site in Aramon, in the Gard, the wastewater treatment plant treats the site's effluent. A recirculation pump submerged in the aeration tank had to be brought out of the water. The operator called on SIDON for emergency work, without draining the tank.

## Five days of preparation

The first call took place on 19 November. The next day, the work was confirmed for Tuesday 24 and the quote signed. The prevention plan was drawn up with the site's HSE department, and SIDON's method statement was sent before the team arrived.

## Safety on site

On arrival, the team attended the site's safety induction. The operator isolated and locked out the tank's electrical and mechanical equipment before the diver entered the water. The dive station and the access ladder were then set up at the edge of the tank.

## A dive with zero visibility

The surface of the tank was covered by a thick, continuous layer of foam and sludge. The diver climbed down the ladder, went through this layer and worked on the pump with no visibility at all. When he came out, his equipment was completely covered in sludge.

## A diver isolated from polluted water

In polluted water, the diver is isolated from the water in the tank: CE-certified rigid helmet, drysuit, air supplied from the surface through the umbilical and a bailout cylinder worn on the back. SIDON divers hold class II, mention A certification.

## Outcome

The pump was brought out of the tank and set down on the ground, next to the structure. Traces of oxidation were visible on the top of the pump, around the lifting handle. The diving equipment was rinsed on site, then cleaned and disinfected at the SIDON depot.

## Project facts

- **Location**: Aramon, Gard (30)
- **Structure**: wastewater treatment plant of an industrial site, aeration tank
- **Type of work**: emergency work on a submerged recirculation pump
- **Techniques**: diving in polluted water, rigid helmet, umbilical, access ladder
- **Team**: SIDON commercial divers, class II, mention A

**Related expertise** · [Commercial divers in wastewater plants, no draining](https://www.sidon-construction.fr/en/divers-wastewater-treatment-plants) · [Diving in polluted water: protecting the diver](https://www.sidon-construction.fr/en/contaminated-water-diving) · [Gates, screens and submerged components](https://www.sidon-construction.fr/en/gates-screens-and-submerged-equipment) · [Underwater works in industrial settings](https://www.sidon-construction.fr/en/industrial-underwater-works)

Projects

## Other projects

[Installation of staff gauges at the Dorlay dam](https://www.sidon-construction.fr/en/projects/staff-gauges-dorlay-dam) — La Terrasse-sur-Dorlay (42) 20 m deep 6 °C water Two staff gauges and their elevation plates installed at more than 20 m on the dam face, in water at 6 °C, by touch. Read the case study

[Restoration of two masonry bridges on the Grand Morin](https://www.sidon-construction.fr/en/projects/masonry-bridge-restoration-coulommiers) — Coulommiers (77) 250 m² repointed 5 wks on site Two masonry bridges on the Grand Morin: four big-bag cofferdams, 250 m² of repointing and low-pressure grout injection. Read the case study

[Refloating a sailing boat in a Natura 2000 area](https://www.sidon-construction.fr/en/projects/sailboat-refloating-natura-2000-hendaye) — Hendaye (64) 1 year aground Natura 2000 protected site Sailing boat aground for nearly a year on the Île aux Oiseaux: refloated with lift bags, then demolished, with materials sorted through a recycling route. Read the case study

---

URL: https://www.sidon-construction.fr/en/projects/emergency-dive-wastewater-plant-aramon
Versions: [fr](https://www.sidon-construction.fr/realisations/intervention-urgence-station-epuration-aramon) · [en](https://www.sidon-construction.fr/en/projects/emergency-dive-wastewater-plant-aramon) · [ru](https://www.sidon-construction.fr/ru/projects/emergency-dive-wastewater-plant-aramon) · [es](https://www.sidon-construction.fr/es/obras/intervencion-urgencia-depuradora-aramon) · [it](https://www.sidon-construction.fr/it/lavori/intervento-urgenza-depuratore-aramon)
SIDON Construction · +33 4 82 83 84 44 · contact@sidon-construction.fr · [Underwater works quote and contact](https://www.sidon-construction.fr/en/contact)